The Interaction of Policy and Enrollment in the Medicaid Buy-In Program, 2005 - Appendix A

Table of Contents | Previous 

Appendix A: Ticket to Work Timeline and Rollout Phase

 

Table A.1. Ticket To Work Program Implementation and Evaluation Timeline
Time Period Implementation Activity or Milestone
1999
December 17 Ticket Act enacted, establishing Ticket to Work Program
2000
Throughout Year SSA Office of Employment Support Programs (OESP) begins to develop principal policies and rules in consultation with SSA deputy commissioners
August to December Draft Notice of Proposed Rule Making (NPRM) negotiated with the Office of Management and Budget
September 29 The Program Manager contract was signed with MAXIMUS, Inc.
November 13 Selection of 13 Phase 1 states announced
December 28 NPRM published, starting the 60-day public comment period
2001
Throughout Year Recommendations for resolving major issues raised by public comment on the NPRM were considered by deputy commissioners
February 26 NPRM public comment period ended. SSA received comments from over 400 interested parties, including federal, state, and local agencies; employers; organizations and advocates for people with disabilities, rehabilitation service providers, disability beneficiaries; and others.
April 13 Request for Proposals on EN contracts were published
October to December Draft final Ticket to Work regulations published
2002
February Selection of Phase 2 and 3 state announced
February 5 Phase 1 begins. Tickets were released to 10 percent of the eligible beneficiaries in Phase 1 states
April Tickets were released to an additional 20 percent of the eligible beneficiaries in the Phase 1 states
May Tickets were released to an additional 30 percent of the eligible beneficiaries in the Phase 1 states
June Tickets were released to the final 40 percent of the eligible beneficiaries in the Phase 1 states
November Phase 2 begins. Tickets were distributed gradually. Ten percent of the Tickets were mailed each month from November 2002 through September 2003 (no tickets were mailed in December).
2003
May 29 Contract was awarded to Mathematica and Cornell for the Evaluation of the Ticket to Work Program, Part A
May 29 Contract was awarded to Mathematica and Cornell for the Evaluation of the Ticket to Work Program, Part B, Survey Data Collection
June National Beneficiary Survey sample was drawn for Round 1
October Participant sample was drawn for Round 1
November Phase 3 begins. Tickets were distributed gradually. Ten percent of the Tickets were mailed each month from November 2003 through September 2004 (no tickets were mailed in December).
2004
February 24 National Beneficiary Survey, Round 1 data collection began
June National Beneficiary Survey sample was drawn for Round 2
September 30 National Beneficiary Survey, Round 1 data collection ended
2005
February 7 National Beneficiary Survey, Round 2 data collection began
June National Beneficiary Survey sample was drawn for Round 3
September 30 National Beneficiary Survey, Round 2 data collection ended
Source: SSA documents and MPR interview with SSA staff

 

Table A.2. States and Territories Included in Each Phase of TTW Implementation
Phase 1: 13 States
Arizona
Colorado
Delaware
Florida
Illinois
Iowa
Massachusetts
New York
Oklahoma
Oregon
South Carolina
Vermont
Wisconsin
Phase 2: 20 States + the District of Columbia
Alaska
Arkansas
Connecticut
District of Columbia
Georgia
Indiana
Kansas
Kentucky
Louisiana
Michigan
Mississippi
Missouri
Montana
Nevada
New Hampshire
New Jersey
New Mexico
North Dakota
South Dakota
Tennessee
Virginia
Phase 3: 17 States + the U.S. Territories
Alabama
California
Hawaii
Idaho
Maine
Maryland
Minnesota
Nebraska
North Carolina
Ohio
Pennsylvania
Rhode Island
Texas
Utah
Washington
West Virginia
Wyoming
American Samoa
Guam
Northern Mariana Islands
Puerto Rico
Virgin Islands
Source: www.ssa.gov/work/ticket_states_announcement.html, accessed August 19, 2003.

 

 